PERI – 3D-printed residential building in Germany

 3D construction printer can be used to create concrete structures in a quick and cost-effective manner, and with a significant degree of design flexibility – without the need for formwork. This makes the procedure an ideal alternative to brick construction.

PERI builds the first 3D-printed apartment building in Germany

  • Building consisting of 5 apartments across 3 floors with approx. 380 square metres of living space constructed using a 3D construction printer
  • The largest printed apartment building in Europe is proof that 3D construction printing is also suitable for the construction of large dwelling units

PERI GmbH has set about printing another residential building using a 3D construction printer, this time in Wallenhausen, Bavaria. At the end of September 2020, the family-owned company announced that work had begun on Germany’s first printed residential house in Beckum, North Rhine-Westphalia.

Giant 3D-printer builds a TWO-STORY house in one piece 🏡 - YouTube

Only two months later, work has begun on the next residential building to make use of 3D construction printing technology. Upon completion, the 5-in-a-block apartment building with around 380 square metres of living space will be the largest printed residential building in Europe. On this project, the printing process is expected to take six weeks.

The planning architect is the architectural firm Mühlich, Fink & Partner BDA from Ulm. The materials used to produce the printable concrete are being sourced from HeidelbergCement. The mixing technology used has been sourced from m-tec mathis technik gmbh. The engineering office Schießl Gehlen Sodeikat assisted with the preparation work for the warrant. The Technical University of Munich planned and carried out the relevant approval tests.

PERI 3D Construction Printing: First 3D-printed residential building in  Germany - YouTube

The residential building in Wallenhausen has a full-length basement and, upon completion, will consist of five apartments across three floors with around 380 square metres of living space. This is not a research or demonstration project. Once construction is complete, the apartments will be rented out in the usual manner. Only one of the apartments will be used as a show apartment.

PERI is using the gantry printer BOD2 for this construction printing project in Wallenhausen. The system has a print head that moves about 3 axes on a securely installed metallic frame. The benefit here is that the printer can move along its frame to any position within the construction and only needs to be calibrated once. This saves time and cuts costs.

This 3D Printer Builds 3-Bedroom Houses In 24 Hours - YouTube

During the printing process, the printer takes into account the pipes and connections for water, electricity, etc. that are to be laid at a later time. The BOD2 has been certified in such a way that it is possible to carry out work within the printing area while printing is in progress. This means that manual work, such as the installation of empty pipes and connections, can be easily integrated into the printing process.

The “i.tech 3D” material that is being used to print the building in Wallenhausen was developed by HeidelbergCement specifically for 3D printing. “The properties of i.tech3D are tailored to the specific requirements of 3D construction printing using concrete,” says Dr. Jennifer Scheydt, Head of Engineering & Innovation at HeidelbergCement. “Our material has excellent pumping and extruding characteristics and works perfectly with the BOD2 printer.”

https://www.peri.com/en/business-segments/3d-construction-printing.html